SCOPE OF WORK:

Install concrete foundation including pits for equipment. Furnished the steel building materials and installed. Furnished the interior offices and bathroom facilities.

 

CHALLENGES: 

A very short time frame to complete. The owner had equipment being delivered and needed the steel buildings up and in operation to complete their work that was scheduled.

 

DURATION OF PROJECT: 6 months.

 

BUILDING SIZE(s) 

100’ w X 600’ l X 30’ h 